Recently, on the process of public urban planning facilities work, the conflict often occurs.
Especially, the site for hateful infrastructure like wasteplex causes a lot of conflict. So, we need to find the solution for good functional aspects by stud...
Recently, on the process of public urban planning facilities work, the conflict often occurs.
Especially, the site for hateful infrastructure like wasteplex causes a lot of conflict. So, we need to find the solution for good functional aspects by studying conflict which can be occurred on the process of site-decision for urban planning facilities like obnoxious facilities.
A wide area waste incineration landfill in Namyangju-city among public urban planning facilities has been troubled for a long time and the aspect of the conflict showed not only between private and public relations but also between public governments among central government, wide area administration, local government and the Korea Land-Housing Corporation complicatedly.
And at that time, the Ministry of Environment and the Ministry of Construction had different point of view and caused conflict. It was a typical example NIMBY(not in my back yard) facilities which was driven out by new public urban planning work.
Although it is a special case, the conflict under urban planning facilities can be generalized. When urban planning is carried out, it is an important case which must be considered. That is the reason I made a choice the problem as a subject of study.
The purpose of this study is to find a cause of the conflict and to draw a method of the conflict resolution by arranging and analyzing complicated conflict from the site-decision to the completion and operation of the construction for 25 years in the style of documentary through an example of waste incineration landfill site, one of the obnoxious facilities among urban planning facilities.
As frame of study, I arranged all the process from landfill site decision to the completion and operation in the style of chronicles. And I found the cause of conflict on the process of business and draw the method of improvement by applying and analyzing Pondy's Dynamic Model of Conflict Case and Kochan's Legal Capacity Model of Conflict.
As a result of study, I knew that the conflict among public governments which had been concealed , at the stage of early business planning, began to expressed gradually and as the business was advanced in earnest, the hidden conflict between public governments, between public and private relations and between private relations was exposed prominently.
Especially, after landfill site had been determined, a plan for Housing-Land Development was designated, and the conflict was gradually changed and the dispute extended over a long period of time by negative external resistance. It gives suggestions to leave much room for improvement on the process of urban planning and carrying out city planning.
For a remedy, first, in case of obnoxious facilities among urban planning facilities work, Government Ministries and local government through the feedback have to improve business system to prevent conflict of each projects. And government has to take up a positive attitude and have a progressive conflict system in case of the douted long-term conflict project.
Second, the receptive capacity through the empowerment of residential community has to be seized by government, and the method to minimalized conflict must be prepared among the central government, a wide area administration and local government through the close mutual cooperation.
Third, from the stage of making a plan for an urban planning facilities like obnoxious facilities, resident delegation should have a voice in the management of the state affairs.
Finally, when large scaled urban planning works like Housing-Land Development is carried out, the information of near seated obnoxious facilities must be institutionalized to open it.