이종석(Jong-Seok Lee),문봉수(Bong-Soo Moon),강원탁(Won-Tag Kang),김경석(Kyeong-Seok Kim) 대한전기학회 2009 대한전기학회 학술대회 논문집 Vol.2009 No.7
According to the 4th BPE(Basic Plan for long-term Electricity Supply and Demand), Electricity demand of Jeju island in 2012 will be reached to 682㎿. Jeju island will be faced with severe shortage of electricty, also needed to find transport route to supply green energy which will be made from "Carbon free island" energy policy toward land at that time. For that reason, The plan which construct 400㎿ size HVDC connection line was decided for potential supply stabilization and transportation of green energy. KEPCO organized special construction office not only to observe the successful project completion which aims 2011 December but also to build up professional manpower. KEPCO is putting spur to the HVDC project these days. Construction site of converter stations has been already confirmed and contracts of cable, converter have done as per turn-key early this year. On this report, we would like to discuss about project scheme, main characteristics of system, and the furture progress plan of "Jindo~Jeju HVDC construction project expecially converter station part" which is being pushed by KEPCO.
이종석(Jong-Seok Lee),문봉수(Bong-Soo Moon),송삼섭(Sam-Seob Song),홍순명(Soon-Myung Hong) 대한전기학회 2009 대한전기학회 학술대회 논문집 Vol.2009 No.7
KEPCO signed up with LS CABLE as a contractor for HVDC submarine cable construction in February 2009. The desk research has been completed in may 2009. Also, Cable route and the protection method will be selected by November 2009. The tentative cable route between Jindo and Jeju which is consisted of sea farms and shipping route zone will reach almost 105㎞. The oceanographic survey for the selection of protection method will be carried out and the survey lists are consisted of MBES, SSS, CPT, ADSP. The protection methods such as burial, Concrete Mattress, UP Pipe, Rock Berm will be selected as per each condition of sea area after the oceanographic survey is completed. Kepco has developed variable methods based on the maintenance experience for HVDC submarine cable between HAENAM and JEJU. Based on the such a accumulated know-how, it can be expected for the confidence and stability of the 2nd HVC project to be improved.