    정보시스템 프로젝트의 위험요인과 실패유형에 관한 연구

    한글로보기

    https://www.riss.kr/link?id=A105013253

    • 0

      상세조회
    • 0

      다운로드
    서지정보 열기
    • 내보내기
    • 내책장담기
    • 공유하기
    • 오류접수

    부가정보

    다국어 초록 (Multilingual Abstract) kakao i 다국어 번역

    As the e-Business expands its area and lots of Information
    System projects are planned and carried out, the failures
    from these projects are increasing. From the project
    manage ment point of view, the exclusion of these failures is
    necessary when operating the information system projects.
    To do this, the thorough identification of the risk factors that
    might occur in the project and tight management of them
    should be exercised throughout the whole project period.
    Based on the solid background of literature reviews, surveys,
    and interviews with the specialists in the field, this paper
    newly developed the lists of risk factors that are also ranked
    in their of importance, which can significantly influence the
    IS projects.
    This study grouped the risk factors into the three failure
    types - time(schedule), cost(budget), and the quality
    (performance) related types. The list of risk factors then,
    were measured based on these three areas separately.
    The different views of the consultants and the system
    developers on the risk factors were participated for the
    comparison purposes for their roles in the projects.
    This research was accomplished by adoption to the domestic
    information system environment. The results indicated that
    the correlations between the risk factors and the failure types
    are significant. The current study can provide a base for
    understanding the risk factors in the IS project, so that tight
    monitoring and successful manage ment can systematically
    reduce the number of failures of the future projects.
    번역하기

    As the e-Business expands its area and lots of Information System projects are planned and carried out, the failures from these projects are increasing. From the project manage ment point of view, the exclusion of these failures is necessary when oper...

    As the e-Business expands its area and lots of Information
    System projects are planned and carried out, the failures
    from these projects are increasing. From the project
    manage ment point of view, the exclusion of these failures is
    necessary when operating the information system projects.
    To do this, the thorough identification of the risk factors that
    might occur in the project and tight management of them
    should be exercised throughout the whole project period.
    Based on the solid background of literature reviews, surveys,
    and interviews with the specialists in the field, this paper
    newly developed the lists of risk factors that are also ranked
    in their of importance, which can significantly influence the
    IS projects.
    This study grouped the risk factors into the three failure
    types - time(schedule), cost(budget), and the quality
    (performance) related types. The list of risk factors then,
    were measured based on these three areas separately.
    The different views of the consultants and the system
    developers on the risk factors were participated for the
    comparison purposes for their roles in the projects.
    This research was accomplished by adoption to the domestic
    information system environment. The results indicated that
    the correlations between the risk factors and the failure types
    are significant. The current study can provide a base for
    understanding the risk factors in the IS project, so that tight
    monitoring and successful manage ment can systematically
    reduce the number of failures of the future projects.

    더보기

    분석정보

    View

    상세정보조회

    0

    Usage

    원문다운로드

    0

    대출신청

    0

    복사신청

    0

    EDDS신청

    0

    동일 주제 내 활용도 TOP

    더보기

    주제

    연도별 연구동향

    연도별 활용동향

    연관논문

    연구자 네트워크맵

    공동연구자 (7)

    유사연구자 (20) 활용도상위20명

    인용정보 인용지수 설명보기

    학술지 이력

    학술지 이력
    연월일 이력구분 이력상세 등재구분
    2020 평가 신규평가 신청대상 (신규평가)
    2019-12-01 등재 등재후보 탈락 (계속평가)
    2018-12-01 등재 등재후보로 하락 (계속평가) KCI등재후보
    2015-01-01 등재 등재학술지 유지 (등재유지) KCI등재
    2011-01-01 등재 등재학술지 유지 (등재유지) KCI등재
    2008-01-01 등재 등재학술지 선정 (등재후보2차) KCI등재
    2007-01-01 등재 등재후보 1차 PASS (등재후보1차) KCI등재후보
    2005-01-01 등재 등재후보학술지 선정 (신규평가) KCI등재후보
    더보기

    학술지 인용정보

    학술지 인용정보
    기준연도 WOS-KCI 통합IF(2년) KCIF(2년) KCIF(3년)
    2016 0.8 0.8 0.73
    KCIF(4년) KCIF(5년) 중심성지수(3년) 즉시성지수
    0.79 0.86 0.972 0.06
    더보기

    이 자료와 함께 이용한 RISS 자료

    나만을 위한 추천자료

    해외이동버튼