This case study is concerned with the project of the explosive demolition for the DCRE Incheon plant located in Hakik district in Incheon city. The building was severely aging due to the high temperature and sea winds of hundreds of degrees emitted by...
This case study is concerned with the project of the explosive demolition for the DCRE Incheon plant located in Hakik district in Incheon city. The building was severely aging due to the high temperature and sea winds of hundreds of degrees emitted by chimney-shaped steel structures inside the building. Due to this, the concrete of the column and the beam fell off and rusted rebar were exposed, and some of the slabs were severely damaged, making it difficult for workers to access the structure.
Therefore, it is not possible to apply a mechanical demolition method in which heavy equipment enters the interior of the building, and an explosive demolition method was applied to allow the building to be demolished without dismantling the internal facilities of the building. The order of blasting proceeded in the order of ➀ building → ➁ chimney 2 → ➂ chimney 1. A total of 406 electronic detonators (Unitronic 600) was used to sequentially initiate the explosives installed at appropriate in building and chimneys.