      국내 표준품셈 현황 조사 및 원전해체 표준품셈 제정에 관한 고찰 = A Study on the Current Status of Korean Standard Cost Estimates and the Establishment of Standard Cost Estimate for Nuclear Decommissioning

      한글로보기

      https://www.riss.kr/link?id=A108295258

      • 0

        상세조회
      • 0

        다운로드
      서지정보 열기
      • 내보내기
      • 내책장담기
      • 공유하기
      • 오류접수

      부가정보

      다국어 초록 (Multilingual Abstract)

      Recently, interest in the decommissioning of nuclear power plants is increasing due tothe permanent shutdown of commercial nuclear power plants such as Wolsong Unit 1 and Kori unit1. Since there is no experience in decommissioning commercial nuclear power plants in Korea, manypending issues such as development of technology and decommissioning regulations are piled up.
      Among them, pending issues such as waste management measures, and evaluation of decommissioningcosts are classified as issues that must be urgently resolved before decommissioning proceeds. Inparticular, continuous research is required to estimate the cost of decommissioning nuclear powerplants in accordance with the social, institutional, and technical requirements. Therefore, this studyinvestigated the standard cost estimates system in other fields among the domestic construction costcalculation systems. Through this, we investigated and analyzed how the current nuclear power plantdecommissioning cost evaluation is being carried out, and suggested the direction for enacting thestandard cost estimate system for nuclear power plant decommissioning. The direction of enactmentof standard cost estimate system for nuclear power plant decommissioning suggested through thisstudy can be used to introduce standard cost estimate system for nuclear power plant decommissioningbusiness. In addition, it is expected that it can contribute to cost reduction and proper estimation ofexpected cost of nuclear power plant decommissioning in the future.
      번역하기

      Recently, interest in the decommissioning of nuclear power plants is increasing due tothe permanent shutdown of commercial nuclear power plants such as Wolsong Unit 1 and Kori unit1. Since there is no experience in decommissioning commercial nuclear p...

      Recently, interest in the decommissioning of nuclear power plants is increasing due tothe permanent shutdown of commercial nuclear power plants such as Wolsong Unit 1 and Kori unit1. Since there is no experience in decommissioning commercial nuclear power plants in Korea, manypending issues such as development of technology and decommissioning regulations are piled up.
      Among them, pending issues such as waste management measures, and evaluation of decommissioningcosts are classified as issues that must be urgently resolved before decommissioning proceeds. Inparticular, continuous research is required to estimate the cost of decommissioning nuclear powerplants in accordance with the social, institutional, and technical requirements. Therefore, this studyinvestigated the standard cost estimates system in other fields among the domestic construction costcalculation systems. Through this, we investigated and analyzed how the current nuclear power plantdecommissioning cost evaluation is being carried out, and suggested the direction for enacting thestandard cost estimate system for nuclear power plant decommissioning. The direction of enactmentof standard cost estimate system for nuclear power plant decommissioning suggested through thisstudy can be used to introduce standard cost estimate system for nuclear power plant decommissioningbusiness. In addition, it is expected that it can contribute to cost reduction and proper estimation ofexpected cost of nuclear power plant decommissioning in the future.

      더보기

      참고문헌 (Reference)

      1 김재현 ; 이승현, "국내 표준품셈 품의 할증을 활용한 국내 원자력발전소 해체 작업난이도 인자 개선 방안 연구" (사)한국방사선산업학회 16 (16): 63-68, 2022

      2 Kwon J, "The scale of the decommissioning cost estimate of nuclear power plants varies widely"

      3 Kim HG, "Status and plan of development of decommissioning nuclear power plant dismantling technology" 34 (34): 33-35, 2014

      4 Nuclear Safety and Security Commission, "Regulations on the Preparation of Plans for Decommissioning NPPs" 2022

      5 Korean Mech. Const. Contrators Associtaion, "Mechanical Facilities" 299 : 87-93, 2015

      6 Ministry of Land, Infrastructure and Transport, "Management Regulations of the Cost of Performed Construction and Standard Costing Management Regulations" 2008-2078, 2008

      7 Lee S, "In six years, 200 billion won has risen... Calculation of the cost of decommissioning Kori Unit 1 by rule of thumb?"

      8 Gang S-H, "Development of methodology for cost evaluation of nuclear power plant decommissioning" 7 (7): 33-34, 2009

      9 Oh C-J, "6500 → 7500 → 850 billion… Nuclear decommissioning cost snowball"

      10 Korea Institute of Civil Engineering and Building Technology, "2022 Standard Costing of Construction"

      1 김재현 ; 이승현, "국내 표준품셈 품의 할증을 활용한 국내 원자력발전소 해체 작업난이도 인자 개선 방안 연구" (사)한국방사선산업학회 16 (16): 63-68, 2022

      2 Kwon J, "The scale of the decommissioning cost estimate of nuclear power plants varies widely"

      3 Kim HG, "Status and plan of development of decommissioning nuclear power plant dismantling technology" 34 (34): 33-35, 2014

      4 Nuclear Safety and Security Commission, "Regulations on the Preparation of Plans for Decommissioning NPPs" 2022

      5 Korean Mech. Const. Contrators Associtaion, "Mechanical Facilities" 299 : 87-93, 2015

      6 Ministry of Land, Infrastructure and Transport, "Management Regulations of the Cost of Performed Construction and Standard Costing Management Regulations" 2008-2078, 2008

      7 Lee S, "In six years, 200 billion won has risen... Calculation of the cost of decommissioning Kori Unit 1 by rule of thumb?"

      8 Gang S-H, "Development of methodology for cost evaluation of nuclear power plant decommissioning" 7 (7): 33-34, 2009

      9 Oh C-J, "6500 → 7500 → 850 billion… Nuclear decommissioning cost snowball"

      10 Korea Institute of Civil Engineering and Building Technology, "2022 Standard Costing of Construction"

      11 Korea Mechanical Construction Contractors Association, "2021 Standard Costing Manual of Information & Communication Contractors" 2020

      더보기

      분석정보

      View

      상세정보조회

      0

      Usage

      원문다운로드

      0

      대출신청

      0

      복사신청

      0

      EDDS신청

      0

      동일 주제 내 활용도 TOP

      더보기

      주제

      연도별 연구동향

      연도별 활용동향

      연관논문

      연구자 네트워크맵

      공동연구자 (7)

      유사연구자 (20) 활용도상위20명

      이 자료와 함께 이용한 RISS 자료

      나만을 위한 추천자료

      해외이동버튼