The purpose of this study was development of assessment technique in case of Dam construction. In order to confirmation of assessment technique. Yun-Chun Dam was assessed in May 4th and July 6th-7th, 1996
There were designed 5 assessment process for ...
The purpose of this study was development of assessment technique in case of Dam construction. In order to confirmation of assessment technique. Yun-Chun Dam was assessed in May 4th and July 6th-7th, 1996
There were designed 5 assessment process for landscape assessment of Dam construction.
First, identified systematically all the potential landscape and visual impacts of the development separately.
Second, compared the sources of impact with landscape and Visual receptors by matrices.
Third, developed a structured field survey form for selected viewpoints across the study area. The survey form permits recording of both objective description and subjective impressions of landscape, as well as details of landscape condition and trends for change.
Forth, selected landscape control points in the main dam site. upstream area. and downstream area.
Fifth, developed significance thresholds to classify the sensitivity of receptors and the magnitude of change according to reference points along a continuum. And majority or few viewers affected, localized dweller or other visitors affected element were included.
Sixth, results of the Yun-Chun Dam case study was helped to separate fact from interpretation, and to simplify discussion and agreement on the significance of landscape impacts.